Project Leader:  Assistant Supt. of Instruction

 

Project Team

Leadership/ School Vision

PR

Purchasing/

Funding

Hardware/

Network/

Security

Software/

Training

Implementation

 

Evaluation

Curriculum

Discipline

Policies

Multimedia
Policies

Superin-

tendent

Super-intendent

Asst. Supt. Of Finance/Operations

Computer Operations Manager

 

 

Instructional Tech Coordinator

 

 

HS Director, Principals

 

 

District

Assessment Director

 

Asst. Supt. Teaching/Learning

Director of Pupil Personnel

Coordinator of PR

Cabinet  

PR- print,

web

Business Manager

HS Technicians

Director of PD

 

Staff Developers

eLearning Vice Principal

 

Freshman Academy Teacher

HS Counselor

 

HS Student

Instructional Technology Coordinator

 

 

HS Director

 

HS Asst. Principal in charge of Discipline

HS Vice Principal

Instructional Tech Coordinator

PR- video

Personnel Director

District

Technicians

School STC’s

eTeam

Curriculum Team

HS Staff Developers

HS Teacher

 

HS Media
Specialists

Computer Operations Manager

PR- events

HS Director (teacher stipends/grants)

Vendors

eTeam

 

Vendors

Student Help Desk

HS  Teacher

 

 

HS Teachers

HS Parent  & Student

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

DATE

TASK

DATE Completed

May

Begin videotaping project

 

May

Identify student target group

May 19, 2003

 

May

Contact State Department about leasing with NON-KETS funds, legal?, can lease non-KETS contract equipment

 

May

Create Specs for pilot computers –hardware and software, network hardware, network licenses, recharging bays, spare, CD DUPLICATOR, machines/harddrives/batteries/drive re-image without losing documents, ANAT and Management, calculator, curriculum sites, Beyond Books, Spectrum, Curriculum Pathways, KVL,Office with FrontPage

May 19th

May

Identify teacher target group

 

Mid-May

May

Procure teacher and school buy-in (what are we going to require that teachers do?)

May 29, 2003

June 2

Apple Leadership Institute

June 2, 2003

June

Begin Website for project

 

June

Put out RFP for computers to potential vendors to provide up to X models of pilot machines (include training requirement)

 

June

Evaluate potential pilot machines- choose X?

 

June

Order notebooks(Stu, Linda, Technicians, HS Vice Principal, Instructional Tech Coordinator, teachers, students) include 1 model each for Student Helpdesk

 

June

Receive notebooks into inventory-MAC

 

June

Distribute notebooks to teachers-MAC

 

June

If Apple is chosen, order STI Classroom Web

 

June

Determine set of peripherals needed at each school (camcorders, still cameras, dedicated student printers for each area, scanners, projectors, etc)

 

June

Order wireless access points for rooms of teachers participating in pilot other critical areas of access (lobbies, media center, bus pickup, etc.)

Peripherals

 

June

Begin training technicians for notebook support

 

June

Explore textbook alternatives

 

June

Identify teacher and student training needs

(individual log-ins, e-mail to students (distribution lists, personal folders), Outlook Calendar, OS, basic fixes & patches, Curriculum Pathways, Backing up, graphing calculator for Intel and OS10 , iClassroom etc)  Make sure software list correlates.

Schedule vendor training for teachers

 

July

Create instrument to evaluate laptops (problems, repairs)  and impact for students, teachers, parents, tech staff, serviceability

Create student, parent, teacher surveys

 

July

Install & test wireless access points in schools and principal’s offices

 

July

Receive notebooks into inventory

 

July

Distribute notebooks to teachers

 

July

Training Team collaborate with Curriculum MONTHLY

 

July

Begin training teachers

Begin creating training handbook

 

July

Receive peripherals and deliver to Media Centers

 

July

Develop plan for after-school access and remote access (MESH) (for free and reduced lunch students?) and support, Adelphia, OMU, Kenergy, Ethics On-Line,

 

July

Develop plan for subject-specific software such as software provide along with a textbook

 

July

Configure notebooks for network access, proxy, security, print access, etc., homework drop boxes, assignments folder, application folder/PC Updater files, access outside state firewall for student e-mail, VNC, proxy, plug-ins, VPN Contivity client, Exchange 2003 for student e-mail, VNC Macintosh Runtime Java, Flash, Quicktime, Acrobat Reader etc., Nettrekker, Curriculum Pathways, Office with Frontpage, shortcut to Kentucky Virtual Library, Spectrum client, student e-mail addresses

 

July

Develop plan for in-school and out of school support

 

August

Training Team collaborate with Curriculum MONTHLY

 

August

Revisit  Policies- AUP, in-school and out of school, mesh bookbags, supplies (who buys CDRWs?, 2.4 G cordless phones)

 

August

Send letter to parents/ students

(parent notification and announcement of meeting, explanation, student survey of computer skills)

 

August

Re-image Teacher MACS

 

August

Jeremy, Brian begin mornings at DCHS, AHS (as needed until student receive notebooks, then regularly until things settle down.)

 

 

Mid -September

Parent Meeting – AUP, insurance

 

 

September

Training Team collaborate with Curriculum MONTHLY

 

 

Mid- September

Distribute notebooks to students with restore CD

 

September

Train students(student login, e-mail, video editing, video out,)

 

September

Begin 4-12 support shift Sunday-Thursday

 

Late -September

Install equipment for after-school access

 

Later - September

Implement after-school access and support

 

September – End of Pilot

On-going training for teachers and students

Keep detailed account of problems, successes

 

 

October

Training Team collaborate with Curriculum MONTHLY

 

 

November

Training Team collaborate with Curriculum MONTHLY

 

 

December

DCHS Pilot ends

 

January

Cannes Festival” and Student Evaluation Meeting

 

Feb - March

Evaluate network & email server needs for full implementation

 

Early March

Administer instrument to evaluate laptops and impact to students, teachers, parents, tech staff

 

March

Tally results of evaluation and report to cabinet

 

March

Final vendor chosen for full-scale project

 

March

Order notebooks for the rest of the faculty

 

April

Re-visit implementation plan with knowledge learned during pilot.

 

April

Plan summer training

 

 

Repeat steps above for full project

 

May

Provide notebooks to the rest of the faculty

 

May

Faculty required to attend Notebook training to receive notebooks

 

April

Purchase new student mail server, file server, wireless access points

 

July

Faculty required to attend 1-1 Notebook training

 

August

Departmental eLearning Training on opening days